| Line 9: | Line 9: | ||
| Production at Bombardier of the additional 600 will fall into step immediately behind the original run of 1,900, putting the run dates at January to July 1986 inclusive. | Production at Bombardier of the additional 600 will fall into step immediately behind the original run of 1,900, putting the run dates at January to July 1986 inclusive. | ||
| - | An interesting note on the label ‘Additional 600” is that a lot of people out there assumed that “additional” meant “over and above entitlement’. Several queries have already been received at the Directorate of Land Requirements to the effect, “How do I get some of those additional new ILTIS you’re buying?” The answer as pointed out earlier, is that you don’t, unless you are one of those previously destined to end up with a Tonka Toy. So, for want of a better name, the Additional 600 will now join the Original 1,900 to became the new fleet of 2,500 ILTIS 1/2 ton trucks...which is what we asked for in the first place! | + | An interesting note on the label “Additional 600” is that a lot of people out there assumed that “additional” meant “over and above entitlement’. Several queries have already been received at the Directorate of Land Requirements to the effect, “How do I get some of those additional new ILTIS you’re buying?” The answer as pointed out earlier, is that you don’t, unless you are one of those previously destined to end up with a Tonka Toy. So, for want of a better name, the Additional 600 will now join the Original 1,900 to became the new fleet of 2,500 ILTIS 1/2 ton trucks...which is what we asked for in the first place! |
| ==== General Project Update ==== | ==== General Project Update ==== | ||
| Line 39: | Line 39: | ||
| === Rationalle === | === Rationalle === | ||
| - | A RAN-D test of initial production vehicles is, in fact, a scientific experiment where a test sample of vehicles is selected at random from a production line and subjected to the environment in which the vehicle must survive after it is introduced to the field. During the test all the support training, manuals, special tools and test equipment available were employed to evaluate them before introduction. During the test the vehicles performed the mission for which they were designed, over the types of terrain they will experience. They were driven by non-trade drivers (male and female), regular force and militia from various units in Canada. The purpose of the test was to determine if the vehicles could meet the RAM-D specifications, | + | A RAM-D test of initial production vehicles is, in fact, a scientific experiment where a test sample of vehicles is selected at random from a production line and subjected to the environment in which the vehicle must survive after it is introduced to the field. During the test all the support training, manuals, special tools and test equipment available were employed to evaluate them before introduction. During the test the vehicles performed the mission for which they were designed, over the types of terrain they will experience. They were driven by non-trade drivers (male and female), regular force and militia from various units in Canada. The purpose of the test was to determine if the vehicles could meet the RAM-D specifications, |
| === Design of the RAM-D Test === | === Design of the RAM-D Test === | ||
| Line 86: | Line 86: | ||
| As stated in the ILTIS Main Contract, if the vehicle fails to meet the RAM-D test requirement, | As stated in the ILTIS Main Contract, if the vehicle fails to meet the RAM-D test requirement, | ||
| - | === ILTIS Reliability Re-Test — Results | + | === ILTIS Reliability Re-Test — Results |
| |< 600px - 100px >| | |< 600px - 100px >| | ||
| | Total Kilometers Driven | 32,918.5 km | | | Total Kilometers Driven | 32,918.5 km | | ||
| Line 98: | Line 98: | ||
| === Retrofit Arising from RAN-D Test === | === Retrofit Arising from RAN-D Test === | ||
| - | Following both RAM-D and RAN-D retest, a series of modifications have been implemented on the assembly line for the 800 vehicles that are not already built. The majority of the vehicles are still sitting in the yard at Bombardier’s plant in Valcourt, Quebec where another line is now operating to retrofit these vehicles with the following modifications: | + | Following both RAM-D and RAM-D re-test, a series of modifications have been implemented on the assembly line for the 800 vehicles that are not already built. The majority of the vehicles are still sitting in the yard at Bombardier’s plant in Valcourt, Quebec where another line is now operating to retrofit these vehicles with the following modifications: |
| - Fuel pump replacement. | - Fuel pump replacement. | ||
| Line 231: | Line 231: | ||
| ==== Status of Publications ==== | ==== Status of Publications ==== | ||
| - | |< 600px 130px 130px - - >| | + | |< 700px 160px 160px - - >| |
| ^ ^ ^ Status | ^ ^ ^ Status | ||
| ^ Description ^ CFTO Number ^ Provisional | ^ Description ^ CFTO Number ^ Provisional | ||
| - | | Lubrication Chart | C-30-108-000/ | + | | Lubrication Chart | [[bombardier: |
| - | | Operators Manual | C-30-108-000/ | + | | Operators Manual |
| - | | Maintenance Manual | C-30-108-000/ | + | | Maintenance Manual |
| - | | Shop Overhaul Manual | C-30-108-000/ | + | | Shop Overhaul Manual |
| - | | Parts Manual | C-30-108-000/ | + | | Parts Manual |
| *Was Delivered by PMO MOST in Dec. 85. | *Was Delivered by PMO MOST in Dec. 85. | ||
| - | It is to be noted that the self-recovery (Unstucker) is not included in the ILTIS Operators Manual, due to testing various systems for compatibility with the vehicle and the manual being in the final stages of production. As of this writing, the kit has been tested, approved and procedures for installation and operation of this kit have been produced by the PMO MOST staff as CFTO-C-30-108-000/ | + | It is to be noted that the self-recovery (Unstucker) is not included in the ILTIS Operators Manual, due to testing various systems for compatibility with the vehicle and the manual being in the final stages of production. As of this writing, the kit has been tested, approved and procedures for installation and operation of this kit have been produced by the PMO MOST staff as CFTO [[bombardier: |
| + | ==== Spare Parts ==== | ||
| + | Logistic support is the key to the successful introduction of the ILTIS Canadian into the Canadian Forces. The objective of the Initial Provisioning process was to identify and procure a range of 2,510 line items of spare parts (both consumable and repairable), | ||
| + | The process of identifying, | ||
| + | |||
| + | Early in the planning stage, we were well aware that the spare parts identified and ordered during the Initial Provisioning Process could not possibly be available in the supply depots before the actual delivery of the vehicle. Consequently, | ||
| + | |||
| + | Although the immediate spares and IP spares purchases should support any potential maintenance problems, a spare parts order agreement has been reached with the contractor for the provision of emergency spares. Basically this agreement will allow units with immediate operational requirement (Ex: Training) to obtain spare parts support for the ILTIS vehicle directly from Bombardier as and when required until the immediate and IP spare support provision becomes available. Units are reminded as outlined in message MOST 85041 151657Z August 1985 that parts demanded through the emergency parts agreement must proceed as follows. Units are to raise a Q.D message in accordance with Annex B Chapter 7 of CFP 181. Q.D messages are to be addressed to DPSL 3-2 and must include NSN and contractors number. This agreement will terminate in January 1986 but will be renewed if necessary. | ||
| + | |||
| + | Because the parts manual for the ILTIS Canadian will not be completed until late 1986. An interim parts manual will be produced by PMO MOST Staff and distributed to all units by the end of 1985. All amendments to the interim parts manual will be published and distributed to units periodically. | ||
| + | |||
| + | ==== Packaging and Preservation ==== | ||
| + | Spare engines and spare transmissions for the ILTIS are referred to as ‘“dressed-up engines and dressed-up transmissions.” An engine or a transmission from its metal container is completely dressed and ready to be installed in the vehicle. This will permit quick removal and replacement of engines and transmissions under adverse field conditions. | ||
| + | |||
| + | Part break down of dress-up components are listed in parts manual [[bombardier: | ||
| + | |||
| + | === Dressed-Up Engine Description === | ||
| + | (a) engine;\\ | ||
| + | (b) oil pressure switch (gauge and light);\\ | ||
| + | (< | ||
| + | (d) alternator with pulley and adjusting arm assy;\\ | ||
| + | (e) V Belts;\\ | ||
| + | (f) water pump with pulley;\\ | ||
| + | (g) clutch plate;\\ | ||
| + | (h) clutch;\\ | ||
| + | (j) release bearing with packing and springs;\\ | ||
| + | (k) intermediate plate with gasket;\\ | ||
| + | (m) block heater assy;\\ | ||
| + | (n) gasket and nuts (exhaust manifold); and\\ | ||
| + | (p) engine mounts. | ||
| + | |||
| + | === Dressed-Up Transmission Description === | ||
| + | (a) transmission; | ||
| + | (b) clutch plate disc;\\ | ||
| + | (< | ||
| + | (d) clutch release lever;\\ | ||
| + | (e) transmission support; and\\ | ||
| + | (f) gaskets. | ||
| + | |||
| + | === Metal Container === | ||
| + | An agreement with the main Contractor has been reached forthe design, manufacture and testing of a suitable metal container to house the 1.7 litre engine and the transmission. These containers will provide the supply system with a capability of long-term indoor and outdoor storage. The design parameters were established to provide a strong rugged container fitted with air pressure and relief valve, reliable lifting hooks and capable of withstanding an all weather environment. The design also provided for a fourway fork lift and stacking facilities. Enough containers have been manufactured to accommodate all 300 spare engines and 200 transmissions held in supply depots. | ||
| + | |||
| + | A cylindrical type metal container with modified rubberized mold is also being used to house the rear differential assembly. | ||